top of page
STEPHENSON CONSTRUCTION
REGIONAL PROFILE
LONDON & SOTUH
Current Projects
Jubilee House, Stratford
Student Accomodation
Client Unite
Main Contractor RG Group
Architect Allford Hall Monaghan Morris
Engineer Apex Consulting
An overall programme of 90 weeks has been set for the execution this project. The scope of work for the Substructure includes Capping Beam, Temporary Works Installation, Bulk Excavation and Drainage - all incorporating Top-down Construction techniques. The Superstructure will be formed by the construction of a Slipform Core followed by 36 Floors of Reinforced Concrete working within a 3 Floor External Protection Screen