Project Update: Feeder Road, Bristol RG Group
Block A: Roof completion was achieved last week, with upstands work currently ongoing.
Core A/B: Concrete pouring was completed, and we are now in the process of preparing to strip the jump platforms.
Block B: Level 10 was successfully poured on Wednesday.
Block C1: Preparations were made for the Level 8 roof pour, which was scheduled for Friday.
Block C2: The Level 8 roof was poured, and upstands work has commenced.
The project is progressing well, thanks to the continued efforts of the entire team.