New Contract Award - Jubilee House, London

A 90-week timeline has been set for the thorough execution of a student accommodation project, covering a spectrum of critical tasks. The scope of work includes Basement Bulk Dig, Capping Beam installation, Groundworks, Drainage implementation, and the construction of a Slipform Core. This ambitious undertaking also involves the assembly of a 36-storey Reinforced Concrete (RC) frame, incorporating top-down construction techniques.